Chapter 1: Understanding the hardening market

With prices for CAR and EAR insurance rising for the first time in many years, Patrice Nigon asks: ‘How did we get here?’

The soft phase of the cycle within engineering and construction was so prolonged, a hard insurance market is a situation that many in the industry have little to no prior experience in. In discussions related to pricing for typhoon-exposed business, there is increasingly a need to communicate that price was not the issue: There is simply very little capacity currently available.

The increase in commercial insurance rates on line within the construction and engineering is following a broader global trend, and it is a long time in coming after many years of rate erosion. It is important to understand how we got here, so that we can build a market that is altogether more sustainable and less volatile going forward, to the benefit of all parties.

Growing claims severity

Among the factors that led to today’s hardening market is a change in claims experience, with a shift towards more severe losses. In the past, engineering and construction was not a volatile line of business – the largest claims were in the region of $50m to $100m. In today’s market, it is not unusual to experience losses in excess of $1 billion. This has fundamentally changed the nature of the business, particularly as engineering is a long-tail line of business.

There are a number of reasons for increasing claims severity. One is the growing size and complexity of projects – new construction methods are constantly enabling us to break new ground and execute methods of construction that may have been unthinkable even a decade ago. However, with these feats of engineering (see box-out examples) come bigger and ever-more complex exposures.

Take the skyline of the City of London, which boasts a series of magnificent buildings with unusual nicknames such as the Shard, the Gherkin, Walkie Talkie and the Cheesegrater. These buildings – many of which went up in the last decade – made use of highly sophisticated, cutting-edge technology to quite literally achieve new heights in architectural design. But when you insure projects like this, there is an element of entering the unknown, which makes underwriting even more complicated.

As claims severity has increased it has become apparent that many within the sector had been overoptimistic in their pricing. Put simply, they had not charged adequate premium to put into reserves to pay for the losses that would not materialise for several years after the project had begun. As a result, we saw a market correction begin to take place, with some of the more opportunistic carriers deciding to cut their losses and exit as performance deteriorated.

This boom and bust attitude towards engineering and construction insurance is one of the factors that contributes to the volatility of the business. As capacity floods into the sector, it creates a soft market.

A boom and bust cycle

It is easy for new entrants to make mistakes, given that losses can take time to materialise and because engineering and construction is such a specialised class of business with so much variety, and very real potential for severity losses.

Newcomers have a tendency to pursue market share at the expense of profits, and during the first two or three years this tactic can work well and the business can generate strong results. It is generally not until a few years down the line that it becomes apparent the business has been underpriced and that’s when losses start to hit the balance sheet.

When results deteriorate, carriers may decide to cut their losses and pull back capacity or exit the market altogether. Over the past two to three years, in particular since Lloyd’s began its Decile 10 performance review, we have seen a number of syndicates exit the engineering and construction space.

This has sparked a contraction of capacity, causing insurance rates to harden and leaving insurance buyers and brokers navigating a challenging market in which premiums are going up and capacity is becoming harder to secure. These market conditions have been exacerbated by the COVID situation and the uncertainty surrounding the ultimate cost of claims emanating from the pandemic, leading carriers to prioritise growth in short-tail classes of business that offer the benefits of immediate profitability.

And so this pattern of behaviour continues until the next generation, when history may once again repeat itself. To avoid this kind of volatility and the challenges of a hardening market, it is essential that engineering and construction is no longer considered a niche play which can simply be turned on and off depending on prevailing market conditions. Carriers in this space need to take a long-term view and become credible partners while brokers have their part of play in emphasising the importance of experience over price.

Delay in Start Up insurance

Delay in Start Up (DSU) insurance is one example of a specialist cover that demands a high level of underwriting expertise. DSU offers cover against the financial consequences of a loss or damage to the contract works causing a delay in the completion of a project. Its purpose is to transfer delay risks on projects that are privately financed by banks, to ensure the contractor will remain solvent and be able to replay their loan on time.

The growth in demand for DSU cover can be traced back to a longer term shift in global privatisation. Whereas most large infrastructure projects used to be funded by the state, increasingly there has been a shift to private financing schemes.

An increase in the use of project finance in more recent times has led to a growth in the DSU market. The limited, or non-recourse, nature of project finance brings an increasing risk exposure for both principals and contractors. In a worst-case scenario, the bank needs to know the borrowers’ loan obligations will continue to be met.

Major construction and engineering projects are extremely complicated, typically involving scores of suppliers and contractors. Each party has a schedule of works and this fits into the overall time schedule and planning of the project. When a claim occurs it can be challenging for the loss adjusters to quantify the total cost of the delay.

Maintaining insurance standards at an appropriate level for all parties involved in DSU insurance demands prudent underwriting, adequate pricing, clearly drafted wordings, comprehensive progress monitoring and thorough claims investigation routines. While it is one thing for underwriters to quantify a potential loss, or even the frequency of potential losses, quantifying the financial impact of a delay requires more advanced knowledge.

As part of their due diligence around project finance, lenders bring in engineers to study the project, identify risks and quantify potential delays using various scenarios. This could be the lockdown of a country or a natural catastrophe event, for instance. But these scenario analysis reports – an essential tool for assessing DSU risks – do not always reach the underwriters.

Another aspect which is often misunderstood is the possibility of liquidated ascertained damages (LADs) due from the contractor for causing delays. These type of delays are generally excluded under DSU insurance, because the onus is on the contractors to ensure the project goes ahead smoothly. Regular progress reports are one way to ensure all parties are on top of target completion dates.

Patrice Nigon is head of construction and engineering, APAC, at Swiss Re Corporate Solutions

Four feats of engineering

The Hong Kong-Zhuhai-Macau Bridge, Hong Kong

In November 2018, after nine years of construction, Hong Kong-Zhuhai-Macau Bridge, the world’s longest sea crossing, opened to traffic.

The 55km crossing consists of three cable-stayed bridges and link roads in the three cities, reducing the travelling time between Hong Kong and Macau/Zhuhai from an hour’s ferry ride to a 40-minute car journey.

Al Hamra Tower, Kuwait

The Al Hamra Tower is the world’s tallest structure to have a continuous stone façade. The building has a distinctive form in response to the harsh climatic conditions. The design eliminates all south-facing offices while providing 270 degrees-wide view of the waters around.

Öresund Bridge and Drogden Tunnel, Denmark

This combined railway and motorway bridge across the Öresund strait between Sweden and Denmark. The bridge runs nearly eight kilometres (five miles) from the Swedish coast to the artificial island Peberholm in the middle of the strait. The crossing is completed by the 4km Drogden Tunnel from Peberholm to the Danish island of Amager.

Hornsea Project One, UK

When fully operational, Hornsea One will be the largest offshore wind array in the world, nearly double the size of the world’s largest. With a capacity of 1.2GW, it comprises 174 8MW turbines, each with a wingspan of over 164 metres.

 

 

About the author

Patrice Nigon

Head, Engineering & Construction APAC, Swiss Re Corporate Solutions

1 comment

Leave a Reply to GABRIEL GONZALEZ Cancel reply

Welcome to The Journal

Welcome to The Journal, StrategicRISK ’s series of interactive online books for professionals in the corporate risk management and insurance sector. The Journal is published in partnership with Swiss Re Corporate Solutions. For more information about StrategicRISK click here.

ABOUT SWISS RE CORPORATE SOLUTIONS

Swiss Re Corporate Solutions provides risk transfer solutions to large and mid-sized corporations around the world. Its innovative, highly customised products and standard insurance covers are backed by its industry-leading claims service. Visit corporatesolutions.swissre.com